Motorized Shade Site Commissioning Acceptance Checklist

Record installed opening, mechanical operation, commands, feedback, exceptions, retests and release status without pre-filling a PASS.

Quick Answer

Commissioning acceptance records the installed result at the actual opening. Start with the released configuration and any bench-test baseline, then verify mechanical operation and only the functions applicable to the selected control path. Use PASS, FAIL, NOT_TESTED or NOT_APPLICABLE. Record exceptions, owners and retests before the named authority releases that scope.

Bench Test and Site Commissioning Are Different

Test-stage boundary
Record Where / purpose Does not prove
A27 bench record Representative hardware before site repetition Installation, field wiring, final grouping or site network behavior
Site commissioning dossier Installed opening under field power/control conditions Long-term performance, unrelated openings or functions not tested
Handover index Transfers accepted records and ownership That every open issue is closed unless listed as such

Site Commissioning Acceptance Dossier

Installed opening acceptance
Domain Record Result field
Identity Opening ID, approved configuration, installed motor/controller/version PASS/FAIL/NOT_TESTED/NOT_APPLICABLE
Mechanical Mounting, unobstructed travel and applicable stops/limits Observed result and exception
Local command Open, close, stop and local fallback where applicable Expected / observed
Group / preset / scene Only functions in the approved selected path Expected / observed
Feedback / central control Only documented interface and feedback expectations Expected / observed
Network-dependent operation Defined onsite/remote path and applicable failure behavior Expected / observed
Release Open issue, retest reference, responsible party and authority Held / partial / accepted per signed record

Use Status Words Precisely

PASS

Observed result meets the agreed criterion for this configuration and revision.

FAIL

Observed result does not meet it; record owner and corrective/retest reference.

NOT_TESTED

No evidence was collected. It is not a pass.

NOT_APPLICABLE

Function is outside the approved configuration; include the reason.

Exception and Retest Loop

  • Record the field condition and exact opening.
  • Separate mechanical, power, interface, programming and network observations.
  • Assign the issue to the responsible project party; do not diagnose from status alone.
  • Reference the corrected revision or action.
  • Retest only affected criteria and preserve prior results.
  • Release only the scope named by the acceptance authority.

Download the Site Acceptance Record

Download Site Commissioning Acceptance Dossier (XLSX)

All result cells default to NOT_TESTED or blank. No PASS is pre-filled. The workbook separates openings, issues and retests.

For coordination across pre-wire, installation, commissioning and handover, use the Pre-Wire & Commissioning Checklist. Record results only after the actual check.

What Saiwenna Can Review

Commissioning review handoff
Buyer provides Saiwenna reviews Output
Released equipment/configuration and opening IDs Supplied-scope identity and documentation Identity discrepancies and required evidence
Expected functions and bench reference Model/interface boundaries Applicable-function questions
Field results, photos and issue log Observed symptom against supplied scope Technical information for responsible-party review; not blanket site approval

Send a Reviewable Brief

Send opening/configuration list, approved functions, bench reference, field exceptions, retest owners and intended release authority.